Canning Vale, WA·Kitchen·15 October 2025·$28K–$35K

Canning Vale Kitchen Renovation

From estimate to final fit-off: how we planned, priced, and delivered.

Canning Vale Kitchen Renovation - Before renovation
Before

This Canning Vale kitchen renovation represents a complete transformation of an outdated space into a modern, functional kitchen that combines style with practicality. The project, completed over 7 weeks, demonstrates how careful planning, accurate cost estimation, and skilled execution can dramatically improve both the functionality and value of a home.

The homeowners came to us with a vision for a spacious, modern kitchen that would serve as the heart of their home. Through our detailed estimate process, we identified the scope of work needed: complete demolition of existing fixtures, installation of custom cabinetry, new flooring, updated electrical and plumbing systems, professional tiling, and comprehensive fit-off. The estimated cost range of $28K–$35K reflected the scale and quality of materials chosen, including premium cabinetry with white-matt finish and brushed brass gold handles, engineered stone benchtops, and large-format splashback tiles.

What makes this project particularly noteworthy is the attention to detail at every stage. From the initial demolition that carefully preserved structural integrity, to the precision installation of custom cabinetry, to the final touches of indirect lighting around the island bar. Each phase was executed with professional expertise. We'll walk you through each stage of the process, showing you exactly what happened, when it happened, and how the costs were allocated.

1

Demo

2–3 days

Canning Vale Kitchen Renovation - Demo stage 1
Demo
Canning Vale Kitchen Renovation - Demo stage 2
Demo

The demolition phase began with careful removal of all existing kitchen fixtures, including old cabinetry, appliances, and fittings. The renovator's team systematically stripped out outdated electrical and plumbing connections, ensuring all services were properly isolated and capped for safety. This process exposed the underlying wall and floor structures, allowing for thorough inspection to identify any hidden issues such as water damage or structural concerns. All materials were disposed of responsibly.

2

Cabinetry Installation

3–5 days

Canning Vale Kitchen Renovation - Cabinetry Installation stage
Cabinetry Installation

Prior to installation, several weeks were dedicated to preparation work including detailed design planning, sourcing and ordering the engineered stone benchtop, and pre-fabricating the cabinet frames. This preparatory phase ensured all components were ready before the on-site installation began. With the space cleared and prepared, the renovator began installing the custom kitchen cabinets featuring a white-matt finish and brushed brass gold handles. The cabinetry was carefully measured and planned to maximize storage and functionality. Each cabinet was installed with precision, ensuring proper leveling and secure attachment to walls. Soft-close hardware was integrated throughout, providing a premium feel and reducing wear on the cabinetry. The installation process included both base and overhead cabinets, creating a cohesive and functional kitchen layout.

3

Flooring

2–3 days

Canning Vale Kitchen Renovation - Flooring stage
Flooring

While flooring replacement is not included in every kitchen renovation, this project involved a complete flooring replacement throughout the space. After the base cabinets were partially installed, hybrid flooring in a clean wood tone was laid across the entire kitchen area. Flooring and painting are often the most transformative elements in a renovation, as they cover large surface areas and dramatically change the color and texture of the space. The installation of the clean wood tone flooring replaced the old, worn tile floor, creating a fresh and modern foundation that significantly improved the overall atmosphere of the kitchen.

4

Tiling

1 day

The splashback tiling was one of the most visually impactful stages of the renovation. The renovator installed large-format 1500x750mm tiles with meticulous attention to spacing and alignment. Each tile was carefully positioned using proper tile adhesive, ensuring consistent grout lines and perfect alignment. The tiles were set with precision, creating a seamless and professional finish. After installation, the renovator grouted the joints and sealed all edges to ensure durability and easy maintenance. Large-format tiles offer a significant advantage: with fewer grout lines compared to smaller tiles, there is less surface area for dirt and grime to accumulate, making cleaning and maintenance much easier. The final result is a stunning splashback that serves as both a functional surface and a design feature.

5

Electrical & Plumbing & Fit-off

4–5 days

Canning Vale Kitchen Renovation - Electrical & Plumbing & Fit-off stage
Electrical & Plumbing & Fit-off

The final stage involved comprehensive electrical and plumbing work, along with complete fixture fit-off. The renovator installed new power points strategically positioned for kitchen appliances, ensuring adequate capacity for modern electrical demands. Lighting circuits were wired throughout, including the installation of indirect lighting around the island bar and cooktop area, creating both functional task lighting and ambient atmosphere. All plumbing connections were completed, including sink water supply and drain connections. The renovator then reconnected all services that had been isolated during demolition, including dishwasher and cooktop electrical connections. The fit-off process involved installing all final fixtures, connecting appliances, and ensuring everything was properly tested and functioning. This comprehensive stage brought the entire renovation together, transforming the space into a fully functional, modern kitchen.

Canning Vale Kitchen Renovation - After renovation
After
Canning Vale Kitchen Renovation - After renovation 2
After
Canning Vale Kitchen Renovation - After renovation 3
After

Transformation Summary

This Canning Vale kitchen renovation represents a complete transformation from an outdated, inefficient kitchen space into a modern, efficient kitchen that maximizes functionality and workflow. The 7-week project involved comprehensive demolition of all existing fixtures, including old cabinetry, appliances, and fittings, creating a clean slate for the new modern design. The installation of comprehensive electrical and plumbing systems ensures optimal functionality for years to come.

The new kitchen design focused on efficiency and workflow optimization. A spacious island bar was incorporated to increase workspace and functionality, with drawers and a dedicated microwave space integrated into the island design, creating a thoughtful layout that considers the natural flow of movement in the kitchen. The base cabinets were designed with a bin drawer positioned next to the sink, allowing for convenient waste disposal right where it's needed most. This thoughtful design consideration enhances daily usability and maintains a clean, organized workspace.

The professional tiling work with large-format 1500x750mm splashback tiles creates a stunning, seamless finish with minimal grout lines, making cleaning and maintenance easier. The clean wood tone hybrid flooring replaced the old, worn tile floor, dramatically transforming the space's atmosphere. The carefully curated fixture selection, including white-matt finish cabinetry with brushed brass gold handles and engineered stone benchtops, creates a cohesive, contemporary aesthetic. All fixtures were carefully installed and connected, ensuring everything functions perfectly.

The final result is a spacious, modern, and highly efficient kitchen that successfully combines style with practicality. The thoughtful design choices, from the spacious island bar with integrated storage to the strategically placed bin drawer, create a kitchen that not only looks beautiful but also functions seamlessly in daily use. The quality materials and professional execution have created a space that not only improves daily living but also significantly increases the home's value. This renovation demonstrates how a well-planned project with careful attention to workflow and efficiency, executed by skilled professionals, can transform a space into an open, modern, and highly functional kitchen.

Project Cost Breakdown

Total Project Cost

$28K–$35K
Demolition$1.2K–$2.0K
Cabinetry$8K–$12K
Flooring$2.5K–$4.0K
Electrical$1.5K–$2.5K
Tiling$3K–$5K
Fit-off$1.5K–$2.5K
ℹ️Estimates include labour costs only. Materials and supplies (tiles, fixtures, etc.) are not included.

Project Details

Size: Big
Scope: Kitchen: Demo + Cabinetry + Flooring + Electrical + Tiling + Fit-off
Duration: ~7 weeks

Materials & Specifications

Kitchen Cabinetry
White-matt finishBrushed brass gold handle
Benchtop
Engineered stone 40mmWaterfall ends
Tiles
1500x750 splashback
Appliances
Integrated dishwasher900mm cooktop